SR 89/Fanny Bridge Community Revitalization Project - Phase 2 Complete Street Improvements and Meeks Bay Path
Project Number
03.02.01.0008
Action Priority
Build and Enhance Transit Systems
Implementers
U.S. Federal Highway Administration, Tahoe Transportation District
Supporting Agencies
California Department of Transportation, California Department of Transportation, U.S. Federal Highway Administration
Primary Contact
Matt Ambroziak (matthew.ambroziak@dot.gov)
Stage
Completed
Duration
2013 - 2020
Total Project Cost
$6,700,000
Funding Request
$0
Transportation Program
Build and Enhance Transit Systems
The project scope includes to components:
1. The Meeks Bay Trail project includes construction of a 0.7 mile paved, shared use path between the Meeks Bay Resort and Sugar Pine Resort. 75% of the project includes retaining walls and also includes a new bridge. The new bridge and retaining walls will be constructed with GRS-IBS foundations to save costs, construction time, and impacts.
2. Construction of bike paths, sidewalk, curb and gutter in Tahoe City as part of the Truckee River Bridge Project.
Targeted Performance Measures
Miles of Pedestrian and Bicycle Routes Improved or Constructed
Threshold Categories
Air Quality
Meeks Bay Trail Completed
Location
Targeted Funding
Secured Funding: California Active Transpo... (Caltrans), $1,100,000
Secured Funding: California Active Transpo... (Caltrans), $3,614,300
Secured Funding: Federal Lands Access Program ... (FHWA), $1,985,700