U.S. Forest Service - Lake Tahoe Basin Management Unit
Supporting Agencies
Unknown or unspecified
Primary Contact
Brian Garrett (brian.garrett@usda.gov)
Stage
Implementation
Duration
2008 - 2027
Total Project Cost
$4,617,000
Funding Request
$0
Sustainable Recreation Program
Improve Public Recreation Facilities
Retrofit access road to improve visitor safety and water quality protection, improve pier and other resort facilities. BMP retrofit plans were incorporated into the Forest Service’s prospectus for a new 30-year special use permit to operate the facility and bring it into compliance with regulations including those that protect Lake Tahoe’s water clarity. Pier replacement completed.
Targeted Performance Measures
No Expected Accomplishments provided
Threshold Categories
Water Quality
Roundhill Access Ramp
Location
Targeted Funding
Secured Funding: Unknown or Unassigned, $2,800,000