Black Bart Area Fire Protection Water Infrastructure
Project Number
02.01.03.0015
Action Priority
Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
Implementers
South Tahoe Public Utility District
Supporting Agencies
U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Donielle Morse (dmorse@stpud.us)
Stage
Completed
Duration
2019 - 2023
Total Project Cost
$3,236,688
Funding Request
$0
Community Wildfire Protection Program
Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
The Black Bart Project installed 7,700 linear feet of new 6-inch water main to replace the existing 1- and 2-inch diameter steel water main that serves the properties. Nine new fire hydrants would be installed that would be accessible from the public right of way.
The project improves water supply enhancing fire protection capabilities on private, local, state, and federal lands by increasing fire flow volumes and coverage area.
Targeted Performance Measures
No Expected Accomplishments provided
Threshold Categories
Vegetation Preservation
Crews work to repair a water leak found during waterline installation on Black Bart
Location
Targeted Funding
Secured Funding: Lake Tahoe Restoratio... (USFS - LTBMU), $635,338