Lake Tahoe EIP

Terrace View Sewer Line Burke Headwaters Restoration

Project Number
01.02.01.0109
Action Priority
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
Nevada Tahoe Conservation District
Supporting Agencies
Nevada Tahoe Conservation District
Primary Contact
Meghan Kelly (mkelly@ntcd.org)

Stage
Planning/Design
Duration
2024 - 2025
Total Project Cost
$750,000
Funding Request
$750,000
Watershed Restoration Program Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Between Terrace View and N. Benjamin Road, there is an export sewer line under a branch of Burke Creek that will be relocated out of the stream zone as part of its life span replacement. This project proposes to restore the SEZ that has been impaired by the dirt sewer line access road and trails.

Targeted Performance Measures

  • Acres of SEZ Restored or Enhanced

Threshold Categories

  • Fisheries
  • Soil Conservation
  • Vegetation Preservation
  • Water Quality
road in SEZ to access sewerline 
(Timing: Before) (~2,280 KB)
Credit: NTCD road in SEZ to access sewerline

Location

Targeted Funding

Secured Funding: Nevada Tahoe Conservancy (NTCD), $1,000

Targeted Funding: Lake Tahoe Restoratio... (USFS - LTBMU), $750,000

Photos

No additional photos provided


Project Fact Sheet Data as of 06/06/2025