Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
U.S. Forest Service - Lake Tahoe Basin Management Unit, Nevada Tahoe Conservation District
Supporting Agencies
U.S. Forest Service - Lake Tahoe Basin Management Unit, U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Theresa Cody (theresa.cody@usda.gov)
Stage
Implementation
Duration
2018 - 2026
Total Project Cost
$4,000,000
Funding Request
$0
Watershed Restoration Program
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Restoration of Saxon Creek targeting the eroding channel, removal of a fish passage barrier, and restoration of three meadows. The watershed above the road is no longer connected to the floodplain due to previous land uses and conifer encroachment. The project includes NEPA and permitting. This restoration project will occur in three phases. Phase 1: Completed 2018. Replacement of aquatic organism passage barrier at Fountain Place Road. Phase 2: Completed 2022, Adapt. Mgmt 2023. Restore 1,000 feet of channel and floodplain upstream and downstream of the bridge installation area. Phase 3: Channel and meadow restoration in three meadows (60 acres total). Anticipated implementation 2026.
Targeted Performance Measures
Acres of SEZ Restored or Enhanced
Linear Feet of Stream Channel Restored or Enhanced
Threshold Categories
Fisheries
Soil Conservation
Water Quality
October 2022_Completed project looking upstream towards bridge
Location
Targeted Funding
Secured Funding: Lake Tahoe Restoratio... (USFS - LTBMU), $950,000
Secured Funding: U.S. Forest Service (USFS - LTBMU), $2,000,000
No Funding Source Identified
Photos
Before
Aquatic organism passage needs improvements at Saxon Creek crossing