Lake Tahoe EIP

Third Creek/Incline Creek Restoration-Phase II Culvert Replacement

Project Number
01.02.01.0014
Action Priority
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
Incline Village General Improvement District
Supporting Agencies
Unknown or unspecified
Primary Contact
HUDSON KLEIN (hwk@ivgid.org)

Stage
Completed
Duration
? - 2011
Total Project Cost
$2,279,319
Funding Request
$0
Watershed Restoration Program Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
The second phase of this project includes the replacement of undersized culverts at Incline Way for both Third Creek and Incline Creek. Previous projects restored sections of Incline and Third Creek between Incline Way and Lakeshore Drive. This phase also includes completion of design of the culvert on Incline Creek at Lakeshore Boulevard.

Targeted Performance Measures

No Expected Accomplishments provided

Threshold Categories

  • Fisheries
  • Soil Conservation
  • Water Quality
Fully passable, open bottom culvert on Incline Creek at Incline Way
(Timing: After) (~428 KB)
Credit: TRPA Fully passable, open bottom culvert on Incline Creek at Incline Way

Location

Targeted Funding

Secured Funding: Unknown or Unassigned, $2,279,319

Photos

Before
Impassable culvert on Incline Creek at Incline Way
(Timing: Before) (~491 KB)
Credit: TRPA
Impassable culvert on Incline Creek at Incline Way
Impassable culvert on Third Creek at Incline Way
(Timing: Before) (~505 KB)
Credit: TRPA
Impassable culvert on Third Creek at Incline Way
After
Fully passable, open bottom culvert on Third Creek at Incline Way
(Timing: After) (~314 KB)
Credit: TRPA
Fully passable, open bottom culvert on Third Creek at Incline Way

Project Fact Sheet Data as of 05/05/2024