Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
City of South Lake Tahoe
Supporting Agencies
Unknown or unspecified
Primary Contact
Stan Hill (shill@cityofslt.us)
Stage
Completed
Duration
2006 - 2016
Total Project Cost
$4,903,428
Funding Request
$0
Stormwater Management Program
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Sierra Tract ECP Phase 3/4: Erosion source controls and stormwater treatment facilities associated with grantees roadways. Improvements will include re-vegetation. of disturbed soils (e.g. paved gutters, rock lined channels), infiltration and sedimentation facilities. Phase 3 and Phase 4 were combined to Phase 3/4. Combined Phase 3/4 includes high priority areas that were identified with the PLRM process.
Targeted Performance Measures
Miles of Roads Decommissioned or Retrofitted
Miles of Street Sweeping
Threshold Categories
Soil Conservation
Water Quality
Reconstructed Chris Basin -7/25/16
Location
Targeted Funding
Secured Funding: Unknown or Unassigned, $4,903,428
Photos
During
William Avenue Basin Construction 2015
Curb & Gutter and Drainage Inlet Construction
River Street Infiltration Gallery - under construction