Lake Tahoe EIP

Basin Resource Inventory and Evaluation (BRIE)

Project Number
04.01.02.0048
Action Priority
Implement Programmatic Monitoring and Reporting
Implementers
U.S. Forest Service - Lake Tahoe Basin Management Unit
Supporting Agencies
California Tahoe Conservancy, U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Sarah Muskopf (sarah.muskopf@usda.gov)

Stage
Planning/Design
Duration
2018 - 2028
Total Project Cost
$930,000
Funding Request
$0
Science Program Implement Programmatic Monitoring and Reporting
The USFS Lake Tahoe Basin Management Unit will conduct inventories and post-implementation monitoring in the UTR and Ward Creek watersheds. The need for these efforts is two-fold. Inventories are needed to determine the status of habitat and sensitive species. This information provides data for project level analysis but also identifies where restoration actions are needed. Post-implementation monitoring allows land managers to determine the success of restoration efforts, identify if adaptive management is needed, and/or where additional restoration actions are warranted.

Targeted Performance Measures

No Expected Accomplishments provided

Threshold Categories

  • Fisheries
  • Soil Conservation
  • Vegetation Preservation
  • Water Quality
  • Wildlife

No Key Photo provided for this Project

Location

Targeted Funding

Secured Funding: California Tahoe Conservancy (CTC), $300,000

Secured Funding: Southern Nevada Publi... (USFS - LTBMU), $630,000

Photos

No additional photos provided


Project Fact Sheet Data as of 06/17/2024