Lake Tahoe EIP

Tunnel Creek Alternative Trail

Project Number
03.02.02.0091
Action Priority
Build and Enhance Trail Networks
Implementers
Nevada Tahoe Resource Team – Nevada Division of State Parks
Supporting Agencies
Nevada Tahoe Resource Team – Nevada Division of State Lands, Nevada Tahoe Resource Team – Nevada Division of State Parks, Tahoe Fund, U.S. Federal Highway Administration
Primary Contact
Kevin Fromherz (kfromherz@parks.nv.gov)

Stage
Implementation
Duration
2018 - 2024
Total Project Cost
$400,000
Funding Request
$180,000
Transportation Program Build and Enhance Trail Networks
The Tunnel Creek Alternative Trail is a Nevada Division of State Parks project, along with other project partners Nevada Division of State Lands, Tahoe Fund, Great Basin Institute, and TAMBA. It is a 2.28 mile single-track alternative route beginning at the base of the Tunnel Creek canyon with indirect linkage to the Tahoe East Shore Trail and ending with linkage to the south end of the Incline Flume Trail. The need for the trail comes primarily from a desire to address public safety issues between user groups on the very congested Tunnel Creek road. The road is also very sandy and steep, and is responsible for a number of bike accidents every year. The trail will be built in two phases.

Targeted Performance Measures

  • Miles of Trails Developed or Improved

Threshold Categories

  • Recreation
Proposed Trail Alignment
(Timing: Before) (~515 KB)
Credit: Great Basin Institute Proposed Trail Alignment

Location

Targeted Funding

Secured Funding: Nevada State Parks (NV State Parks), $11,500

Secured Funding: Recreational Trails Program F... (FHWA), $72,000

Secured Funding: Tahoe Bonds Act (NDSL), $200,000

Secured Funding: Tahoe Fund (Tahoe Fund), $50,000

Targeted Funding: Land and Water Conservation Fu... (NPS), $180,000

Photos

During
View of new trail and view of Tahoe
(Timing: During) (~4,269 KB)
Credit: TAMBA
View of new trail and view of Tahoe
Sutter Wall Construction
(Timing: During) (~6,251 KB)
Credit: TAMBA
Sutter Wall Construction
TAMBA Constructing Sutter Walls
(Timing: During) (~6,794 KB)
Credit: TAMBA
TAMBA Constructing Sutter Walls
New Trail 
(Timing: During) (~105 KB)
Credit: TAMBA
New Trail
Trail Crew Construction 
(Timing: During) (~259 KB)
Credit: TAMBA
Trail Crew Construction
TAMBA Volunteer Trail Crew
(Timing: During) (~4,561 KB)
Credit: TAMBA
TAMBA Volunteer Trail Crew

Project Fact Sheet Data as of 05/18/2024