Lake Tahoe EIP

TART Capital to Support Unconstrained Service - Short term

Project Number
03.02.01.0048
Action Priority
Build and Enhance Transit Systems
Implementers
Placer County, CA
Supporting Agencies
Unknown
Primary Contact
Kansas McGahan (kmcgahan@placer.ca.gov)

Stage
Terminated
Duration
2018 - 2021
Total Project Cost
$2,000,000
Funding Request
Unknown
Transportation Program Build and Enhance Transit Systems
*This project was terminated on 12/27/16 - It was rolled up into a larger transit capital project, 03.01.02.0056.

Targeted Performance Measures

  • Pounds of Air Pollutants Removed or Avoided by Project

Threshold Categories

  • Air Quality

No Key Photo provided for this Project

Location

Targeted Funding

No Funding Source Identified

Photos

No additional photos provided


Project Fact Sheet Data as of 05/18/2024