Cave Rock Enhancement Project - Phase 1 Recreation Improvements
Project Number
03.01.02.0093
Action Priority
Improve Public Recreation Facilities
Implementers
Nevada Tahoe Resource Team – Nevada Division of State Parks, Nevada Tahoe Resource Team
Supporting Agencies
Unknown or unspecified
Primary Contact
Kevin Fromherz (kfromherz@parks.nv.gov)
Stage
Completed
Duration
2015 - 2016
Total Project Cost
$459,534
Funding Request
$0
Sustainable Recreation Program
Improve Public Recreation Facilities
Phase I Recreation Improvements to the Cave Rock facility include sidewalk replacement and reconfiguration of existing entry lanes and parking to better accommodate circulation and access within the site. This project also included removal of the existing concrete boat ramp located at the southern end of the facility, which has long been out of use and inaccessible. Coverage above high water will be credited for use on other projects within the Park.