2023 STPUD Pioneer Trail Fire Suppression Infrastructure
Project Number
02.01.03.0020
Action Priority
Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
Implementers
South Tahoe Public Utility District
Supporting Agencies
South Tahoe Public Utility District, U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Donielle Morse (dmorse@stpud.us)
Stage
Planning/Design
Duration
2022 - 2026
Total Project Cost
$6,963,201
Funding Request
$1,000,000
Community Wildfire Protection Program
Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
This project installs 11,300 linear feet of new 12 and 16” water mains and 10 fire hydrants on Pioneer Trail from Marshall Trail to Susquehana. This is a sparsely populated road but a main evacuation route and fire break for the community of South Lake Tahoe. There is currently not water service along this route. The project will install fire hydrants at less than 1000 ft spacing in accordance with the Fire Code for undeveloped areas and will provide fire flow in excess of 3000 gpm.
Targeted Performance Measures
Miles of Utility Lines Buried Underground
Threshold Categories
Recreation
Vegetation Preservation
Wildlife
No Key Photo provided for this Project
Location
Targeted Funding
Secured Funding: Lake Tahoe Restoratio... (USFS - LTBMU), $1,411,701
Secured Funding: South Tahoe Public Utility D... (STPUD), $5,551,500
Targeted Funding: U.S. Environmental Protectio... (USEPA), $1,000,000