U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Catherine Howells (chowells@southtahoerefuse.com)
Stage
Planning/Design
Duration
2022 - 2026
Total Project Cost
$3,000,000
Funding Request
$3,000,000
Community Wildfire Protection Program
Reduce Hazardous Fuels
South Tahoe Refuse & Recycling (STR) is exploring the installation of a 125-250kW wood waste gasifier at its South Lake Tahoe facility. Gasification has been around since the early 1800’s – instead of burning, chemical reactions turn the green waste into a gas that is a cleaner substitute for fossil fuels. If installed, the net metering system would offset the majority of grid electricity and natural gas used at the STR site by using 10-15% of the wood waste currently collected by STR, and reduce traffic and emissions from transporting waste material out of the Basin by over 70 truckloads each year.