Brautovich Park SEZ Restoration and Park Rehabilitation Project

Project Number
01.02.01.0091
Action Priority
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
Nevada Tahoe Conservation District
Supporting Agencies
Douglas County, NV, Private, Tahoe Regional Planning Agency, Tahoe Regional Planning Agency
Primary Contact
Meghan Kelly (mkelly@ntcd.org)

Stage
Post-Implementation
Duration
2019 - 2020
Total Project Cost
$527,515
Funding Request
$0
Watershed Restoration Program Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
The Brautovich Park SEZ Restoration and Park Rehabilitation is a joint effort between Douglas County and the Nevada Tahoe Conservation District (NTCD). The Project restored over a half acre of a Douglas County-owned parcel (APN 1319-18-401-003) to historic stream environment zone (SEZ), relocated the existing baseball field and playground to less sensitive lands within the parcel, and upgraded the parking and water quality features to help achieve the Lake Tahoe TMDL. The reconfiguration of the site incorporated improved stormwater treatment and erosion control to bring the parcel into BMP compliance.

Targeted Performance Measures

  • Acres of SEZ Restored or Enhanced
  • Facilities Improved or Created

Threshold Categories

  • Recreation
  • Water Quality
new paved parking, turf field in upland, trail, and restored SEZ below
(Timing: After) (~1,309 KB)
Credit: NTCD new paved parking, turf field in upland, trail, and restored SEZ below

Location

Targeted Funding

Secured Funding: Douglas County General Fund (DGCO), $100,000

Secured Funding: Private Property Owners (Private), $350,000

Secured Funding: SEZ Mitigation Funds (TRPA), $20,109

Secured Funding: WQ Mitigation Funds (TRPA), $57,406

Photos

Before
Water quality feature before
(Timing: Before) (~1,684 KB)
Credit: Douglas County
Water quality feature before
Ball field before
(Timing: Before) (~1,551 KB)
Credit: Douglas County
Ball field before
During
hydroseeding restored and disturbed areas
(Timing: During) (~1,263 KB)
Credit: NTCD
hydroseeding restored and disturbed areas
removing 5-9 feet of fill from the historic SEZ to higher capability land
(Timing: During) (~873 KB)
Credit: NTCD
removing 5-9 feet of fill from the historic SEZ to higher capability land
After
interactive rock features leading to SEZ for public enjoyment
(Timing: After) (~1,355 KB)
Credit: NTCD
interactive rock features leading to SEZ for public enjoyment

Project Fact Sheet Data as of 05/19/2024