Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
California Department of Parks and Recreation
Supporting Agencies
California Tahoe Conservancy
Primary Contact
Rich Adams (rich.adams@parks.ca.gov)
Stage
Deferred
Duration
2016 - 2025
Total Project Cost
$1,500,000
Funding Request
$1,000,000
Watershed Restoration Program
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
The project is in Antone Meadows in Burton Creek State Park in partnership with Tahoe City PUD. Project includes removal of the dam over Burton Creek, relocation of water diversion from Antone Meadow to Lake Tahoe, restoration of meadow and stream channels at dam site, removal of sections of diversion pipe and topographic restoration of pipe road, riparian hardwood restoration around the dam site and meadow, removal of an undersized bridge at the dam and replacement with new bridge which spans the floodplain and allows for access of fire trucks and fuels management equipment.
Targeted Performance Measures
Acres of Forest Fuels Reduction Treatment
Acres of SEZ Restored or Enhanced
Linear Feet of Stream Channel Restored or Enhanced
Miles of Roads Decommissioned or Retrofitted
Threshold Categories
Fisheries
Wildlife
Burton Creek dam
Location
Targeted Funding
Secured Funding: California Tahoe Conservancy (CTC), $150,000
Targeted Funding: Lake Tahoe Restoratio... (USFS - LTBMU), $1,000,000