Lake Tahoe EIP

Stream Environment Zone Utility Crossing Condition Assessment

Project Number
01.02.01.0062
Action Priority
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
South Tahoe Public Utility District
Supporting Agencies
South Tahoe Public Utility District
Primary Contact
Donielle Morse (dmorse@stpud.us)

Stage
Planning/Design
Duration
2021 - 2025
Total Project Cost
$200,000
Funding Request
$50,000
Watershed Restoration Program Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
STPUD has approximately 149 sites in which utility infrastructure (water and sewer lines) are crossing a stream environment zone, literally in the streambed. This project is a condition assessment of each of these 149 sites in order to assess the condition of the current infrastructure and the risk to the SEZ. The assessment would prioritize the sites through a risk assessment and give a generalized "toolbox" approach to stabilizing the infrastructure, to include stream restoration as necessary.

Targeted Performance Measures

  • Acres of SEZ Restored or Enhanced

Threshold Categories

  • Water Quality
STPUD stream environment zone utility crossing assessment locations
(Timing: During) (~804 KB)
Credit: South Tahoe Public Utility District STPUD stream environment zone utility crossing assessment locations

Location

Targeted Funding

Secured Funding: South Tahoe Public Utility D... (STPUD), $150,000

Targeted Funding: South Tahoe Public Utility D... (STPUD), $50,000

Photos

No additional photos provided


Project Fact Sheet Data as of 05/17/2024