Lake Tahoe EIP

Incline Lake Property Planning & Implementation

Project Number
01.02.01.0035
Action Priority
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
U.S. Forest Service - Lake Tahoe Basin Management Unit
Supporting Agencies
U.S. Forest Service - Lake Tahoe Basin Management Unit, U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Theresa Cody (theresa.cody@usda.gov)

Stage
Implementation
Duration
2011 - 2025
Total Project Cost
$2,981,000
Funding Request
$0
Watershed Restoration Program Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Removal of Incline Lake Dam structures, restoration of stream and meadow, and installation of permanent BMPs. NEPA Decision planning/ documentation was accomplished with SNPLMA Funding by 2015. Dam removal was completed in 2020; channel and floodplain through former dam footprint were restored and ditch decommissioned in 2021; boardwalk trail installation across constructed floodplain was constructed in 2022; additional ditch decommissioning and upland disturbed site restoration work occurred in 2023; and the remaining stream and meadow restoration work is planned for 2024.

Targeted Performance Measures

  • Acres of Habitat Restored or Enhanced

Threshold Categories

  • Water Quality
New channel through former dam
(Timing: During) (~3,352 KB)
Credit: LTBMU New channel through former dam

Location

Targeted Funding

Secured Funding: Southern Nevada Publi... (USFS - LTBMU), $2,816,000

Secured Funding: U.S. Forest Service (USFS - LTBMU), $165,000

Photos

Before
Meadow headcut at old Incline Lake
(Timing: Before) (~355 KB)
Credit: TRPA
Meadow headcut at old Incline Lake
During
Boulder in dam
(Timing: During) (~4,172 KB)
Credit: LTBMU
Boulder in dam
Newly constructed floodplain and channel_Sept 2021
(Timing: During) (~7,307 KB)
Credit: USFS LTBMU
Newly constructed floodplain and channel_Sept 2021
After
Newly constructed floodplain_Sept 2021
(Timing: After) (~7,518 KB)
Credit: USFS LTBMU
Newly constructed floodplain_Sept 2021
BDAs in channel and new boardwalk over newly constructed floodplain at former dam location.
(Timing: After) (~6,561 KB)
Credit: Theresa Cody, LTBMU
BDAs in channel and new boardwalk over newly constructed floodplain at former dam location.

Project Fact Sheet Data as of 05/19/2024