Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
U.S. Forest Service - Lake Tahoe Basin Management Unit
Supporting Agencies
Unknown or unspecified
Primary Contact
Brian Garrett (brian.garrett@usda.gov)
Stage
Completed
Duration
? - 2012
Total Project Cost
$2,833,000
Funding Request
$0
Watershed Restoration Program
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
This proposal funds the third phase of the Blackwood Channel and Floodplain Restoration Project. This project abandons a 1/2 mile section of stream channel that was channelized as a result of past land uses associated with a gravel quarry, and restore flows to an adjacent remnant of historic channel that is still largely intact. In addition 7 acres adjacent to the historic channel will be reshaped and stabilized.
Targeted Performance Measures
No Expected Accomplishments provided
Threshold Categories
Water Quality
Blackwood Creek
Location
Targeted Funding
Secured Funding: Unknown or Unassigned, $2,833,000