Highway 50 Echo Summit Bridge Rehabilitation (SHOPP)

Project Number
01.01.02.0005
Action Priority
Operate and Maintain Stormwater Infrastructure
Implementers
California Department of Transportation
Supporting Agencies
California Department of Transportation
Primary Contact
Joan Davis (D3.FTIP@dot.ca.gov)

Stage
Completed
Duration
2014 - 2022
Total Project Cost
$14,758,000
Funding Request
$0
Stormwater Management Program Operate and Maintain Stormwater Infrastructure
On US 50 at Echo Summit Sidehill Viaduct Bridge (#25-0044). Bridge replacement. EA 3F530

Targeted Performance Measures

No Expected Accomplishments provided

Threshold Categories

No Threshold Categories provided
Post Construction
(Timing: After) (~210 KB)
Credit: RE Post Construction

Location

Targeted Funding

Secured Funding: SHOPP Funds (Caltrans), $14,758,000

Photos

No additional photos provided