Hicks Erosion Control Project Phase I

Project Number
01.01.01.0200
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
Nevada Tahoe Resource Team
Supporting Agencies
Nevada Tahoe Resource Team – Nevada Division of State Lands
Primary Contact
Christopher LaCasse (chris.lacasse@lands.nv.gov)

Stage
Completed
Duration
2021 - 2022
Total Project Cost
$79,678
Funding Request
$0
Stormwater Management Program Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
The Hicks Urban Parcel is owned by the State of Nevada and is adjacent to Incline Creek. In the past few years, the site has experienced large scale surface erosion. The first phase of this project will analyze sources of erosion by completing hydrological, geotechnical, and topographical surveys, and prepare conceptual and 75% design documents for restoration and stabilization of the Hicks Urban Parcel. Construction of erosion control and hillside stabilization measures will take place in subsequent phase.

Targeted Performance Measures

  • Disturbed Areas Restored, Enhanced, or Created

Threshold Categories

  • Soil Conservation
  • Water Quality
Post construction, planted and irrigation installed.
(Timing: During) (~5,227 KB)
Credit: Chris LaCasse Post construction, planted and irrigation installed.

Location

Targeted Funding

Secured Funding: Tahoe Bonds Act (NDSL), $79,678

Photos

No additional photos provided


Project Fact Sheet Data as of 11/15/2024