Lake Tahoe EIP

NV Energy Resilience Corridors Projecct

Project Number
02.01.02.0016
Action Priority
Implement Defensible Space on Public and Private Parcels and Utility Corridors
Implementers
U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Brian Garrett (brian.garrett@usda.gov)
Stage
Implementation
Duration
2020 - 2028
Community Wildfire Protection Program Implement Defensible Space on Public and Private Parcels and Utility Corridors
The project will create resilient forests adjacent to approximately 28 miles of NV Energy utility infrastructure on the Nevada side of the Tahoe Basin. The project is designed to treat in 3 zones, Zone 1 is the area immediately adjacent to utility infrastructure (15'), Zone 2 is up to 175' from utility infrastructure and Zone 3 can extend up to 1000' feet from the utility infrastructure. The project will thin forest to improve forest health, remove trees that could grow into or fall on power lines and reduce hazardous fuels.

Key Accomplishments

  • Acres of Forest Fuels Reduction Treatment: 852.7 acres

Threshold Categories

  • Vegetation Preservation

No Key Photo provided for this Project

Location

Expenditures

Expenditures by Funding Source to Date: $14,392,000
(Estimated Cost: $21,000,000)
Lake Tahoe Restoratio... (USFS - LTBMU): $2,500,000

Southern Nevada Publi... (USFS - LTBMU): $6,567,000

U.S. Forest Service (USFS - LTBMU): $325,000

Nevada Energy (NV Energy): $5,000,000

Photos

No additional photos provided


Project Fact Sheet Data as of 05/06/2025