Lake Tahoe EIP

Basin Resource Inventory and Evaluation (BRIE)

Project Number
04.01.02.0048
Action Priority
Implement Programmatic Monitoring and Reporting
Implementers
U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Sarah Muskopf (sarah.muskopf@usda.gov)
Stage
Planning/Design
Duration
2018 - 2028
Science Program Implement Programmatic Monitoring and Reporting
The USFS Lake Tahoe Basin Management Unit will conduct inventories and post-implementation monitoring in the UTR and Ward Creek watersheds. The need for these efforts is two-fold. Inventories are needed to determine the status of habitat and sensitive species. This information provides data for project level analysis but also identifies where restoration actions are needed. Post-implementation monitoring allows land managers to determine the success of restoration efforts, identify if adaptive management is needed, and/or where additional restoration actions are warranted.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

  • Fisheries
  • Soil Conservation
  • Vegetation Preservation
  • Water Quality
  • Wildlife

No Key Photo provided for this Project

Location

Expenditures

Expenditures by Funding Source to Date: $160,250
(Estimated Cost: $930,000)
Southern Nevada Public Land Ma... (BLM): $160,250

Photos

No additional photos provided


Project Fact Sheet Data as of 05/05/2024