Hwy 50 at Apache Ave Pedestrian Improvements (SHOPP Minor A)
Project Number
03.02.02.0107
Action Priority
Build and Enhance Trail Networks
Implementers
California Department of Transportation
Primary Contact
Sukhi Johal (D3.FTIP@dot.ca.gov)
Stage
Planning/Design
Duration
2024 - 2027
Transportation Program
Build and Enhance Trail Networks
Near Meyers, at Apache Avenue (PM 70.94/71.06). Relocate mid-block crossing and install Rectangular Rapid Flash Beacons (RRFB). EA 0N910
Key Accomplishments
Accomplishments to be provided upon completion of project
Threshold Categories
Transportation and Sustainable Communities
HMA- This is existing HMA walking path (US 50) that is connecting to trail. This will be removed and reinstalled to US 5O/Apache Ave intersection connecting with new crosswalk.
Location
Expenditures
Expenditures by Funding Source to Date: $271,354 (Estimated Cost: $1,374,000)
SHOPP Funds (Caltrans): $271,354
Photos
Before
New HMA: New HMA walking path will installed to US 50/ Apache Ave intersection.
Refreshing the existing striping in US 50. Pedestrian signs will be relocated to US 50/Apache Ave Intersection.
Existing Crosswalk will be removed that is located in US 50 close to California Agriculture Inspection Station. New crosswalk will be installed in intersection of US 50 and Apache Ave.