South Tahoe Greenway Shared-Use Trail - Phase 1a

Project Number
03.02.02.0002
Action Priority
Build and Enhance Trail Networks
Implementers
California Tahoe Conservancy
Primary Contact
Whitney Brennan (whitney.brennan@tahoe.ca.gov)
Stage
Completed
Duration
2010 - 2018
Transportation Program Build and Enhance Trail Networks
The initial construction phase of the South Tahoe Greenway Shared Use Trail (Greenway), Phase 1a, extends 0.42 miles between Herbert Avenue and Glenwood Way in the heart of the Bijou neighborhood in South Lake Tahoe. Preliminary planning refinements began in 2012 and initial construction occurred in 2015. In 2017 additional project drainage infrastructure was constructed. The next implementation phase of the Greenway, Phases 1b&2, will extend the trail connection south to the Sierra Tract and is described as a separate EIP project.

Key Accomplishments

  • Miles of Pedestrian and Bicycle Routes Improved or Constructed: 0.42 miles
  • Miles of Roads Decommissioned or Retrofitted: 0.1 miles

Threshold Categories

  • Air Quality
  • Recreation
Greenway Bike Trail at Walkup
(Timing: After) (~75 KB)
Credit: Jeanne McNamara Greenway Bike Trail at Walkup

Location

Expenditures

Expenditures by Funding Source to Date: $921,230
(Estimated Cost: $921,230)
California Tahoe Conservancy (CTC): $921,230

Photos

During
Greenway Phase 1a Project Sign
(Timing: During) (~197 KB)
Credit: Jeanne McNamara
Greenway Phase 1a Project Sign
After
Additional Drainage Infrastructure
(Timing: After) (~1,759 KB)
Credit: Cecchi
Additional Drainage Infrastructure
Becka Drive Drainage
(Timing: After) (~3,028 KB)
Credit: Cecchi
Becka Drive Drainage

Project Fact Sheet Data as of 11/15/2024