Van Sickle Bi-State Park Phase 3

Project Number
03.01.02.0123
Action Priority
Improve Public Recreation Facilities
Implementers
Nevada Tahoe Resource Team – Nevada Division of State Parks
Primary Contact
Cassandra Hughes (c.hughes@parks.nv.gov)
Stage
Planning/Design
Duration
2022 - 2026
Sustainable Recreation Program Improve Public Recreation Facilities
Van Sickle Phase 3 is an improvement to the Van Sickle Bi-State Park Phase 1. Nevada State Parks has hired a contractor to design a visitor center, improved parking, and restrooms. The visitor center will include park offices, a gift shop, and interpretive spaces. A multi-use paved path is being planned from the visitor to the center to the state border. The planning team is coordinating occurring with California Tahoe Conservancy to continue the path to Lakeview Parkway. An improved monument is being planned for the Nevada/California Stateline that will include additional interpretive opportunities. Construction is tentatively planned for the summer of 2025.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

  • Recreation
Van Sickle Bi-State Park - lower developed area
(Timing: Before) (~1,387 KB)
Credit: Nevada State Parks Van Sickle Bi-State Park - lower developed area

Location

Expenditures

Expenditures by Funding Source to Date: $288,763
(Estimated Cost: $20,000,000)
Tahoe Bonds Act (NDSL): $288,763

Photos

Before
2nd Floor 30% Design
(Timing: Before) (~82 KB)
Credit: ARG
2nd Floor 30% Design
1st Floor 30% Design
(Timing: Before) (~105 KB)
Credit: ARG
1st Floor 30% Design
During
Van Sickle Entry in CA
(Timing: During) (~113 KB)
Credit: Nevada State Parks
Van Sickle Entry in CA

Project Fact Sheet Data as of 11/15/2024