Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
Implementers
South Tahoe Public Utility District
Primary Contact
Jennifer Marshall (jmarshall@stpud.us)
Stage
Implementation
Duration
2022 - 2027
Community Wildfire Protection Program
Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
This project replaces approximately 15,900 linear feet of waterlines, and install fire hydrants, water main interties, and appurtenances, in two phases. The Herbert-Walkup Waterline Replacement (Phase 1) includes the replacement of approximately 9,400 linear feet of waterline, along with the
installation of 16 fire hydrants and 9 water main interties. The Bijou #1 Waterline Replacement (Phase 2) includes replacement of approximately 6,500 linear feet of waterline, along with the installation of 12 fire hydrants and 7 water main interties.
Key Accomplishments
Accomplishments to be provided upon completion of project
Threshold Categories
Recreation
Vegetation Preservation
Wildlife
Installation of a three-valve cluster connected to existing 6” steel pipe. New 8” C900 will come into third valve.
Location
Expenditures
Expenditures by Funding Source to Date: $8,563,521 (Estimated Cost: $9,000,000)
South Tahoe Public Utility D... (STPUD): $8,563,521
Photos
During
New pipe going into the Pickett neighborhood.
Compaction of the first paving lift in the Pickett neighborhood.
Completed fire hydrant with hydrant valve before backfill.