Lake Tahoe EIP

2023 STPUD Bijou 1 Waterline and Fire Hydrants

Project Number
02.01.03.0021
Action Priority
Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
Implementers
South Tahoe Public Utility District
Primary Contact
Donielle Morse (dmorse@stpud.us)
Stage
Planning/Design
Duration
2022 - 2027
Community Wildfire Protection Program Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
This project replaces approximately 6,000 Linear Feet of 2” and 4” water main that is undersized for supporting fire hydrants in two adjacent, densely populated neighborhoods within the City of South Lake Tahoe. The Takela/Fremont neighborhood is primarily multi-familly residences and a few commercial businesses; the project will install 8” mains and 5 new fire hydrants at less than 500 ft spacing to provide fire flow in excess of 1500 gpm. The Deer Park neighborhood is primarily small, closely spaced early Tahoe cabins; the project will install 8” mains and 15 new fire hydrants at less than 500 ft spacing to provide fire flow in excess of 1500 gpm.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

  • Recreation
  • Vegetation Preservation
  • Wildlife

No Key Photo provided for this Project

Location

Expenditures

No expenditures provided

Photos

No additional photos provided


Project Fact Sheet Data as of 05/05/2024