Slott Peak Waterline Improvements

Project Number
02.01.03.0019
Action Priority
Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
Implementers
Incline Village General Improvement District
Primary Contact
HUDSON KLEIN (hwk@ivgid.org)
Stage
Completed
Duration
2021 - 2022
Community Wildfire Protection Program Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
Replacement of 330 linear feet of 6-inch water main with new 8-inch water main and replacement of one fire hydrant to meet NLTFPD code requirements. This project is a continuation of the multi-year program to replace 1960's era thin wall steel water mains and other deficient water mains. Replacement criteria is twofold: Replace those water mains with the most leaks and in streets with aging pavement. Since our water loss is now less than 6%, our main objective is to work closely with the Washoe County Road Department to replace water mains just prior to the County's repaving the street. Project enhances fire protection capabilities on private, local, state, and federal lands.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

  • Vegetation Preservation
Tie-in location
(Timing: During) (~8,350 KB)
Credit: IVGID Tie-in location

Location

Expenditures

Expenditures by Funding Source to Date: $200,000
(Estimated Cost: $275,000)
Incline Village General Impr... (IVGID): $200,000

Photos

During
General trenching and backfill
(Timing: During) (~7,653 KB)
Credit: IVGID
General trenching and backfill
New Tee
(Timing: During) (~3,652 KB)
Credit: IVGID
New Tee

Project Fact Sheet Data as of 05/05/2024