Lake Tahoe EIP

STPUD Fire Hydrant Upgrades and Improvements Fire Protection Project

Project Number
02.01.03.0017
Action Priority
Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
Implementers
South Tahoe Public Utility District
Primary Contact
Donielle Morse (dmorse@stpud.us)
Stage
Implementation
Duration
2022 - 2024
Community Wildfire Protection Program Upgrade Priority Water Infrastructure to Fight Catastrophic Wildfire
STPUD needs to upgrade and or replace and install approximately 70 fire hydrants throughout its service area to reduce the current deficiencies in fire flow and available fire protection. Project improves water supply enhancing fire protection capabilities on private, local, state, and federal lands by increasing fire flow volumes and coverage area.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

  • Wildlife
856 Roger Avenue Reduced
(Timing: Unknown) (~1,153 KB)
Credit: STPUD 856 Roger Avenue Reduced

Location

Expenditures

Expenditures by Funding Source to Date: $300,000
(Estimated Cost: $750,000)
City of South Lake Tahoe Gene... (CSLT): $300,000

Photos

No additional photos provided


Project Fact Sheet Data as of 05/05/2024