Lake Tahoe EIP

Liberty Utilities- Apache Ave Undergrounding

Project Number
02.01.02.0012
Action Priority
Implement Defensible Space on Public and Private Parcels and Utility Corridors
Implementers
Liberty Cal Peco Electric
Primary Contact
Frank Papandrea (fpapandrea@vailresorts.com)
Stage
Implementation
Duration
2018 - 2021
Community Wildfire Protection Program Implement Defensible Space on Public and Private Parcels and Utility Corridors
0.75 miles of utility undergrounding along Apache Ave in Meyers.

Key Accomplishments

  • Miles of Utility Lines Buried Underground: 0.75 miles

Threshold Categories

  • Scenic Resources

No Key Photo provided for this Project

Location

Expenditures

Expenditures by Funding Source to Date: $1,300,000
(Estimated Cost: $1,500,000)
Liberty Utilities (Liberty): $1,300,000

Photos

No additional photos provided


Project Fact Sheet Data as of 05/07/2024