STPUD Wastewater Treatment Plant Fuels Reduction project

Project Number
02.01.01.0126
Action Priority
Reduce Hazardous Fuels
Implementers
South Tahoe Public Utility District
Primary Contact
Donielle Morse (dmorse@stpud.us)
Stage
Completed
Duration
2020 - 2022
Community Wildfire Protection Program Reduce Hazardous Fuels
South Tahoe Public Utility District treated 100 acres adjacent to the wastewater treatment facility with fuels reduction efforts.

Key Accomplishments

  • Acres of Forest Fuels Reduction Treatment: 104 acres

Threshold Categories

  • Vegetation Preservation
South Tahoe Public Utility District Treatment Plant Fuel Hazard Reduction Project
(Timing: Unknown) (~248 KB)
Credit: Unknown South Tahoe Public Utility District Treatment Plant Fuel Hazard Reduction Project

Location

Expenditures

Expenditures by Funding Source to Date: $322,074
(Estimated Cost: $323,000)
California Tahoe Conservancy (CTC): $322,074