Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
Incline Village General Improvement District
Primary Contact
HUDSON KLEIN (hwk@ivgid.org)
Stage
Completed
Duration
? - 2013
Watershed Restoration Program
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
The fourth phase of this project includes the implementation of many features to reconnect the creek with the floodplain, stabilize steep eroding banks, and increase fish habitat and migration on Third Creek and Incline Creek between Incline Way and State Route 28.
Key Accomplishments
Acres of Habitat Restored or Enhanced: 1.05 acres
Linear Feet of Stream Channel Restored or Enhanced: 1,200 lf
Threshold Categories
Fisheries
Soil Conservation
Water Quality
No Key Photo provided for this Project
Location
Expenditures
Expenditures by Funding Source to Date: $1,631,604 (Estimated Cost: $1,631,604)
Tahoe Bonds Act (NDSL): $601,186
U.S. Army Corps of Engineer... (USACOE): $1,030,418