Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
California Tahoe Conservancy
Primary Contact
Whitney Brennan (whitney.brennan@tahoe.ca.gov)
Stage
Completed
Duration
? - 2009
Watershed Restoration Program
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Slope stabilization and conveyence between Mohican and Erie streets in the Meyers area. Will prevent erosion into an SEZ and be able to convey larger flows.
Key Accomplishments
Acres of Habitat Restored or Enhanced: 0.25 acres
Linear Feet of Stream Channel Restored or Enhanced: 186 lf
Miles of Roads Decommissioned or Retrofitted: 0.03 miles
Threshold Categories
Water Quality
No Key Photo provided for this Project
Location
Expenditures
Expenditures by Funding Source to Date: $5,000 (Estimated Cost: $5,000)