Lake Tahoe EIP

Streets and Roads Operations and Maintenance - NDOT

Project Number
01.01.02.0023
Action Priority
Operate and Maintain Stormwater Infrastructure
Implementers
Nevada Department of Transportation
Primary Contact
Tyler Thew (tthew@dot.nv.gov.)
Stage
Implementation
Duration
2015 - 2050
Stormwater Management Program Operate and Maintain Stormwater Infrastructure
Annual Streets and Roads Operations and Maintenance (existing, does not reflect future TMDL implementation) -- NDOT. This includes all on-going, recurring costs for operations and maintenance of roadways. One-time maintenance is tracked under a different project. Annual operations and maintenance costs must be tracked as part of the Regional Transportation Plan Update.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

  • Water Quality

No Key Photo provided for this Project

Location

Expenditures

Expenditures by Funding Source to Date: $9,095,155
(Estimated Cost: )
Nevada Department of Transpor... (NDOT): $9,095,155

Photos

No additional photos provided


Project Fact Sheet Data as of 12/04/2024