Lake Tahoe EIP

Stormwater Treatment Facilities Operations and Maintenance – City of South Lake Tahoe

Project Number
01.01.02.0013
Action Priority
Operate and Maintain Stormwater Infrastructure
Implementers
City of South Lake Tahoe
Primary Contact
Stan Hill (shill@cityofslt.us)
Stage
Implementation
Duration
2013 - 2040
Stormwater Management Program Operate and Maintain Stormwater Infrastructure
Annual Stormwater Treatment Facilities Operations and Maintenance – City of South Lake Tahoe. If these costs are tracked as part of other maintenance, such as roadway maintenance, implementers should record $0 for this project and make a notation in the notes field of this project and the notes field of the larger maintenance project, providing as much detail as possible about expenditures related to stormwater treatment operations and maintenance. Estimates are fine. Annual operations and maintenance costs must be tracked as part of the Regional Transportation Plan Update.

Key Accomplishments

  • Acres of Forest Fuels Reduction Treatment: 15 acres

Threshold Categories

  • Water Quality
Dry Basin 1 - Glorene and 8th ECP before 2014 maintenance
(Timing: Before) (~2,789 KB)
Credit: Jason Burke Dry Basin 1 - Glorene and 8th ECP before 2014 maintenance

Location