Lake Tahoe EIP

Highway 50 Echo Summit Bridge Rehabilitation (SHOPP)

Project Number
01.01.02.0005
Action Priority
Operate and Maintain Stormwater Infrastructure
Implementers
California Department of Transportation
Primary Contact
Joan Davis (D3.FTIP@dot.ca.gov)
Stage
Completed
Duration
2014 - 2022
Stormwater Management Program Operate and Maintain Stormwater Infrastructure
On US 50 at Echo Summit Sidehill Viaduct Bridge (#25-0044). Bridge replacement. EA 3F530

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

No Threshold Categories provided
Post Construction
(Timing: After) (~210 KB)
Credit: RE Post Construction

Location

Expenditures

Expenditures by Funding Source to Date: $14,094,374
(Estimated Cost: $14,758,000)
SHOPP Funds (Caltrans): $14,094,374

Photos

No additional photos provided


Project Fact Sheet Data as of 04/26/2024