Lake Tahoe EIP

Ralph Tank BMP and SEZ Restoration Project

Project Number
01.01.01.0204
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
South Tahoe Public Utility District
Primary Contact
Yesenia Pacheco (ypacheco@stpud.us)
Stage
Completed
Duration
2011 - 2022
Stormwater Management Program Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Removal of water tank, associated structures and other coverage to access the facility located in SEZ near Bijou Creek. SEZ vegetation has been restored. Parking barriers installed and water spreading BMPs in place on 2 parcels to permit foot access to remaining monitoring well facility. 4,428 sf total coverage removed & banked on APNs 025-551-006 & -007 as part of project.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

  • Soil Conservation
  • Water Quality
  • Wildlife
Pre-construction 
(Timing: Before) (~80 KB)
Credit: STPUD Pre-construction

Location

Expenditures

No expenditures provided

Photos

During
Ralph Tank Demolition
(Timing: During) (~96 KB)
Credit: STPUD
Ralph Tank Demolition
Site Construction
(Timing: During) (~89 KB)
Credit: STPUD
Site Construction
After
Ralph Tank Site Initial Vegetation Establishment
(Timing: After) (~99 KB)
Credit: STPUD
Ralph Tank Site Initial Vegetation Establishment
Ralph Tank Site Vegetation Establishment April 2022
(Timing: After) (~1,845 KB)
Credit: TRPA
Ralph Tank Site Vegetation Establishment April 2022

Project Fact Sheet Data as of 05/05/2024