Ruby Way – Overlook Court Drainage and Erosion Control Project

Project Number
01.01.01.0158
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
City of South Lake Tahoe
Primary Contact
Stan Hill (shill@cityofslt.us)
Stage
Deferred
Duration
2015 - 2024
Stormwater Management Program Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Water quality and erosion control project that will address surface runoff conditions. Existing site conditions include an undersized storm drain collection and conveyance system that is overwhelmed during high intensity storms. Project work will include adding in additional storm drain inlets, adding subsurface storm drain pipes to replace an existing steep rock-lined conveyance channel, and constructing a series of linear storm drain detention basins that will also allow infiltration of stormwater. Project improvements will redirect urban stormwater runoff into a new subsurface conveyance systems; thereby, removing overland surface flow that is impacting private and public property.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

No Threshold Categories provided
Eroding channel discharging sediment onto Ruby Way: 2/8/2016
(Timing: Before) (~2,607 KB)
Credit: Jason Burke Eroding channel discharging sediment onto Ruby Way: 2/8/2016

Location

Expenditures

Expenditures by Funding Source to Date: $202,954
(Estimated Cost: $1,663,000)
City of South Lake Tahoe Gene... (CSLT): $2,500

Proposition 1 (SWRCB): $200,454

Photos

Before
Sediment discharge to Ruby Way
(Timing: Before) (~2,599 KB)
Credit: Jason Burke
Sediment discharge to Ruby Way
Localized flooding during Storm Event 11-10-08 Runoff into adjacent property 
(Timing: Before) (~4,375 KB)
Credit: Stan Hill
Localized flooding during Storm Event 11-10-08 Runoff into adjacent property

Project Fact Sheet Data as of 04/25/2024