Angora Fire Roads Mitigation (Road Decommissioning)
Project Number
01.01.01.0049
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
U.S. Forest Service - Lake Tahoe Basin Management Unit
Primary Contact
Brian Garrett (brian.garrett@usda.gov)
Stage
Completed
Duration
2009 - 2012
Stormwater Management Program
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
In order to mitigate the impact of Forest Service system and non-system roads to surface drainage within and near the Angora Fire area, the USFS planned and implemented Forest Service system road BMP upgrades and realignments, and obliterated segments of non-system roads.
Key Accomplishments
Miles of Roads Decommissioned or Retrofitted: 10.5 miles
Threshold Categories
Soil Conservation
Water Quality
Decompacted & Recontoured NFS Rd North of Boulder Mt. Road
Location
Expenditures
Expenditures by Funding Source to Date: $161,753 (Estimated Cost: $161,753)