Crystal Bay Water Quality Improvement Project Phase II
Project Number
01.01.01.0041
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
Washoe County, NV
Primary Contact
Dave Solaro (dsolaro@washoecounty.gov)
Stage
Completed
Duration
? - 2009
Stormwater Management Program
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
This project will implement source control throughout the project area. Cut/fill slopes were treated with soil conditioning and revegetation, rock slope protection and toe walls. Also road shoulders and compacted areas were addressed through the use of AC grindings and mulch, eco-blocks and revegetation. Stormwater treatment and conveyance will be addressed in a later project phase.
Key Accomplishments
Miles of Roads Decommissioned or Retrofitted: 0.1 miles
Threshold Categories
Water Quality
Eco-block shoulder treatment
Location
Expenditures
Expenditures by Funding Source to Date: $962,301 (Estimated Cost: $962,301)