02.01.02.0029 - Zephyr Heights Community Defensible Space
Duration 2026 - 2029 Planning/Design
Lead Implementer Nevada Tahoe Conservation District
Estimated Total Cost $2,626,845
Threshold Categories Vegetation Preservation
Focus Area Forest Health
Program Community Wildfire Protection Program
Action Priority Implement Defensible Space on Public and Private Parcels and Utility Corridors
For project expenditures & results, see Project Fact Sheet