Transportation Program
Build and Enhance Trail Networks
Continue pedestrian sidewalks, lighting, transit stops, and class II bike lanes from the limits of the completed Phase 1 project (Larch Avenue) to the western limits of Ski Run Boulevard (+.45 Center line Miles).
Key Accomplishments
Accomplishments to be provided upon completion of project
Threshold Categories
Air Quality
On-street parking near Sonora Ave. intersection looking north.
Location
Expenditures
Expenditures by Funding Source to Date: $412,163 (Estimated Cost: $6,149,000)
California Highway Infrastruc... (FHWA): $3,326
Surface Transportation Block ... (FHWA): $361,178
City of South Lake Tahoe Gene... (CSLT): $47,659
Photos
Before
Existing bus stop near Sonora Ave. intersection.
Pioneer Tr. and Sonora Ave. intersection looking west.
Project End – Pioneer Tr. and Ski Run Blvd. intersection looking south.