SR 28 Corridor Management Plan Implementation - Phase 1
Project Number
03.02.01.0009
Action Priority
Build and Enhance Transit Systems
Implementers
Tahoe Transportation District
Primary Contact
Judi Allen (jallen@tahoetransportation.org)
Stage
Completed
Duration
2011 - 2015
Transportation Program
Build and Enhance Transit Systems
This project creates a plan to address environmental, safety, and public access issues associated with uncontrolled access along the East Shore of Lake Tahoe. Phase 1 includes expansion of two existing USFS parking lots, a new park and ride lot at US50/SR28 junction (Spooner) including a permanent AIS inspection station, new transit stops south of Sand Harbor, highway safety improvements including center line rumble strip, guard rail, and improved signage, and other highway operational improvements.
Key Accomplishments
Accomplishments to be provided upon completion of project
Threshold Categories
Air Quality
SR 28 CMP Overall Recommendations Map
Location
Expenditures
Expenditures by Funding Source to Date: $728,512 (Estimated Cost: $7,300,000)