Lake Tahoe EIP

Liberty Utilities Undergrounding- South "Y" Phase IV

Project Number
02.01.02.0009
Action Priority
Implement Defensible Space on Public and Private Parcels and Utility Corridors
Implementers
Liberty Cal Peco Electric, Private
Primary Contact
Frank Papandrea (fpapandrea@vailresorts.com)
Stage
Completed
Duration
2009 - 2011
Community Wildfire Protection Program Implement Defensible Space on Public and Private Parcels and Utility Corridors
0.35 lines of utilities undergrounded on Lake Tahoe Blvd from Sawmill Road to Tahoe Mountain Road.

Key Accomplishments

  • Miles of Utility Lines Buried Underground: 0.25 miles

Threshold Categories

  • Scenic Resources

No Key Photo provided for this Project

Location

Expenditures

Expenditures by Funding Source to Date: $108,975
(Estimated Cost: $108,083)
Liberty Utilities (Liberty): $108,975

Photos

No additional photos provided


Project Fact Sheet Data as of 12/04/2024