Completed
Duration
2006 - 2012
Watershed Restoration Program Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Riparian habitat restoration along General Creek will remove conifers and will include prescribed burns and other management strategies that will mimic natural process (such as fire). Objective is to improve riparian habitat for riparian dependent species.

Key Accomplishments

  • Acres of Forest Fuels Reduction Treatment: 17.5 acres

Threshold Categories

  • Vegetation Preservation

No Key Photo provided for this Project

Location

Expenditures

Expenditures by Funding Source to Date: $320,000
(Estimated Cost: $320,000)
California Department of Park... (CDPR): $320,000