Third Creek/Incline Creek Restoration-Phase III Lakeshore Boulevard Culvert Replacement
Project Number
01.02.01.0042
Action Priority
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
Implementers
Incline Village General Improvement District
Primary Contact
HUDSON KLEIN (hwk@ivgid.org)
Stage
Completed
Duration
? - 2011
Watershed Restoration Program
Restore Priority Meadows, Wetlands, and Lake Tahoe Tributaries
The third phase of this project includes the replacement of an undersized culvert at Lakeshore Blvd for Incline Creek. Previous projects restored sections of Incline Creek between Incline Way and Lakeshore Drive.
Key Accomplishments
Linear Feet of Stream Channel Restored or Enhanced: 130 lf
Threshold Categories
Fisheries
Soil Conservation
Water Quality
open bottom, fully passable culvert on Incline Creek at Lakeshore Blvd
Location
Expenditures
Expenditures by Funding Source to Date: $1,183,660 (Estimated Cost: $1,183,660)
Tahoe Bonds Act (NDSL): $138,363
U.S. Army Corps of Engineer... (USACOE): $1,045,297
Photos
Before
impassable culvert on Incline Creek at Lakeshore Blvd