Stormwater Management Program
Operate and Maintain Stormwater Infrastructure
This project will repair an existing retaining wall along Beowawie Road in Crystal Bay, Nevada. This wall was installed as part of the Crystal Bay Erosion Control Project (1988) and is failing due to extreme runoff during and following the 2017 winter. The failing slope is located within 600 feet of Lake Tahoe, and a complete slope failure would have a negative effect on water quality.
Key Accomplishments
Accomplishments to be provided upon completion of project
Threshold Categories
Water Quality
Completed Beowawie retaining wall from street view
Location
Expenditures
Expenditures by Funding Source to Date: $96,960 (Estimated Cost: $75,000)
TRPA Operations & Maintenance... (TRPA): $35,000
Washoe County General Fund (WACO): $27,319
Washoe County Road Enterprise... (WACO): $34,641
Photos
Before
Failing timber retaining wall at Beowawie
Slope erosion resulting from failing timber retaining wall at Beowawie