Lake Tahoe EIP

US 50 3R Preservation in the Tahoe Basin

Project Number
01.01.01.0173
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
Nevada Department of Transportation
Primary Contact
Chris Holman (cholman@dot.nv.gov)
Stage
Planning/Design
Duration
2017 - 2025
Stormwater Management Program Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
US 50, Douglas County from the CA/NV State line to Kings Canyon Rd, 13.26 (miles) Mill and overlay with ADA, Hydraulic and Safety Improvements. 3R project Package 1 & Package 2

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

  • Air Quality

No Key Photo provided for this Project

Location

Expenditures

Expenditures by Funding Source to Date: $1,549,959
(Estimated Cost: $49,025,000)
Nevada State Gas Tax (NDOT): $1,549,959