Bijou Area Water Quality Improvement Project, Phases 2

Project Number
01.01.01.0160
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
City of South Lake Tahoe
Primary Contact
Stan Hill (shill@cityofslt.us)
Stage
Planning/Design
Duration
2015 - 2026
Stormwater Management Program Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Stabilize roadside shoulders as a means of sediment source control to protect the newly constructed Bijou ECP Phase 1 infiltration basins. Provide distributed infiltration as a form of hydrologic source control, acquire easements and install overflow conveyances where localized flooding results in excessive sediment tracking onto City road network, in order to improve roadway sweeping effectiveness and source control.

Key Accomplishments

Accomplishments to be provided upon completion of project

Threshold Categories

No Threshold Categories provided
Road condition impacts from inadequate drainage and need for source control - Glenwood Way
(Timing: Before) (~3,135 KB)
Credit: Jason Burke Road condition impacts from inadequate drainage and need for source control - Glenwood Way

Location

Expenditures

Expenditures by Funding Source to Date: $10,000
(Estimated Cost: $1,000,000)
City of South Lake Tahoe Gene... (CSLT): $10,000

Photos

Before
Inadequate road drainage impacts ability to use achieve TMDL Road RAM scores - Glenwood Way
(Timing: Before) (~3,883 KB)
Credit: Jason Burke
Inadequate road drainage impacts ability to use achieve TMDL Road RAM scores - Glenwood Way
Inadequate road drainage and road shoulder stabilization - roadway flooding impacts ability to achieve TMDL Road RAM scores
(Timing: Before) (~3,317 KB)
Credit: Jason Burke
Inadequate road drainage and road shoulder stabilization - roadway flooding impacts ability to achieve TMDL Road RAM scores
Road shoulder erosion (Red Lake Road/Walkup Road)
(Timing: Before) (~2,281 KB)
Credit: City of South Lake Tahoe
Road shoulder erosion (Red Lake Road/Walkup Road)
1190 Glenwood
(Timing: Before) (~3,084 KB)
Credit: Chuck Taylor
1190 Glenwood
Flooding at 3403 Janet St (1/20/2019)
(Timing: Before) (~423 KB)
Credit: Chuck Taylor
Flooding at 3403 Janet St (1/20/2019)