Lake Tahoe EIP

Al Tahoe Erosion Control Project

Project Number
01.01.01.0060
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
City of South Lake Tahoe
Primary Contact
Stan Hill (shill@cityofslt.us)
Stage
Completed
Duration
? - 2012
Stormwater Management Program Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
The City of South Lake Tahoe is the implementing agency for this project. The Al Tahoe project area consists of two primary watersheds that drains to several storm drains that collect flow from the Al Tahoe subdivision. The project area is approximately 55 acres (bounded by US 50 to the east, Los Angeles Avenue to the south, Lake Tahoe to the north and Sacramento Avenue to the west) with ~19 acres of impervious area. Included are disturbed earthen road shoulders, single- and multi-family residences, commercial enterprises, and a popular recreation area – Regan Beach.

Key Accomplishments

  • Miles of Roads Decommissioned or Retrofitted: 3 miles

Threshold Categories

  • Soil Conservation
  • Water Quality
Al Tahoe Shoulder Stabilization
(Timing: After) (~147 KB)
Credit: City of South Lake Tahoe Al Tahoe Shoulder Stabilization

Location

Expenditures

Expenditures by Funding Source to Date: $6,181,476
(Estimated Cost: $6,181,476)
American Recovery and Reinves... (ARRA): $2,648,723

Southern Nevada Publi... (USFS - LTBMU): $2,025,253

Proposition 50 (CTC): $1,507,500

Photos

Before
Al Tahoe Pre-Construction
(Timing: Before) (~218 KB)
Credit: City of South Lake Tahoe
Al Tahoe Pre-Construction
Al Tahoe Pre-Construction
(Timing: Before) (~121 KB)
Credit: City of South Lake Tahoe
Al Tahoe Pre-Construction
After
Al Tahoe Shoulder Work
(Timing: After) (~180 KB)
Credit: City of South Lake Tahoe
Al Tahoe Shoulder Work

Project Fact Sheet Data as of 04/18/2024