Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
City of South Lake Tahoe
Primary Contact
Stan Hill (shill@cityofslt.us)
Stage
Completed
Duration
2006 - 2016
Stormwater Management Program
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Sierra Tract ECP Phase 3/4: Erosion source controls and stormwater treatment facilities associated with grantees roadways. Improvements will include re-vegetation. of disturbed soils (e.g. paved gutters, rock lined channels), infiltration and sedimentation facilities. Phase 3 and Phase 4 were combined to Phase 3/4. Combined Phase 3/4 includes high priority areas that were identified with the PLRM process.
Key Accomplishments
Acres of SEZ Restored or Enhanced: 2.25 acres
Miles of Roads Decommissioned or Retrofitted: 3.2 miles
Miles of Street Sweeping: 7 miles
Threshold Categories
Soil Conservation
Water Quality
Reconstructed Chris Basin -7/25/16
Location
Expenditures
Expenditures by Funding Source to Date: $4,903,428 (Estimated Cost: $4,903,428)